The city board has approved staff to proceed with negotiating right of way acquisition for both sides of the Dillard’s property.

Current design of the section between Dillard’s is 90% complete

South Main Project Update

Preconstruction meeting has been held with contractor and work should begin within the next couple of weeks.  The…

State of City Bike Projects

27th Nov, 2013

by

As usual at the monthly meeting of the BFCC (Bicycle Friendly Community Committee) a report of the state of the city’s bike projects was given by John Honeywell.  Mayor Stodola also took the time to speak about the Close the Loop initiative.

Close the Loop:  Work is progressing towards construction of the two termini on…